FOURTH & WILLIAM PARKING STRUCTURE IMPROVEMENT PROJECT

WEEKLY CONSTRUCTION UPDATE:     Week of 06/21/2015

 

 

PLEASE PARDON OUR DUST AND NOISE.

WE’RE IN THE PROCESS OF A STAIR/ELEVATOR MODERNIZATION/REPLACEMENT PROJECT.

FASTER ELEVATORS FOR FASTER ACCESS TO THE DOWNTOWN!

 

 

SAFETY FIRST:

Be sure to follow the pedestrian way-finding signage.

Please slow down while driving thru the structure and be aware of your surroundings.

 

 

WEEKLY PROGRESS:

Construction is ongoing and a great amount of activity is occurring on site

Demolition of existing concrete floor slabs

Trucks will haul away concrete debris from the site

 

Please follow alternate pedestrian route through the Palio Lot

 

 

NEXT WEEK:

Barricading for construction activities will be maintained.

Material deliveries for future stairs/structural steel and door frames will take place

The steel subcontractor will install structural steel

 

 

For more information visit the project website at:

http://www.a2dda.org/current-projects/4th-william-stair-tower-elevator/

 

 

Overall Project Schedule Is Anticipated To Be….

Phase I: Construction of the new stair tower. April 2015 thru Sept 2015.

Phase 2: Demo of existing stair tower, construction of new high speed elevator.  Sept 2015 thru March 2016.

Phase 3: Demo of existing elevator, installation of 2nd new high speed elevator. March 2016 thru Sept 2016.

 

 

Fourth & William Project Manager: Chad Nienhuis - chadn@spencebrothers.com

Fourth & William Site Superintendent: Dave Fewins davefewins@spencebrothers.com

 

 

Project Concerns/Questions- Call 734-761-3582 (open 24/7)