4th & William Project Update (5/20)

Author: Andrea Miller/Wednesday, May 20, 2015/Categories: News, Parking Alerts

PLEASE PARDON OUR DUST AND NOISE. WE’RE IN THE PROCESS OF A STAIR/ELEVATOR MODERNIZATION/REPLACEMENT PROJECT.  FASTER ELEVATORS FOR FASTER ACCESS TO THE DOWNTOWN!

 

SAFETY FIRST:     Be sure to follow the pedestrian way-finding signage. Please slow down while driving thru the structure and be aware of your surroundings.

 

WEEKLY PROGRESS: Construction is ongoing and a great amount of activity is occurring on site. LOUD Demolition of brick/concrete with jackhammers and saws

 

 Please follow alternate pedestrian route through the Palio Lot

 

NEXT WEEK:

 

  • Barricading for demolition activities will be maintained.
  • LOUD demolition (Saws, jackhammers) of the existing brick, and concrete will occur behind fencing and barricades.
  • Trucks will be hauling brick and concrete debris from the project site.

For more information visit the project website at:

http://www.a2dda.org/current-projects/4th-william-stair-tower-elevator/


Overall Project Schedule Is Anticipated To Be….

Phase I:  Construction of the new stair tower. April 2015 thru Sept 2015.

Phase 2:  Demo of existing stair tower, construction of new high speed elevator.  Sept 2015 thru March 2016. Phase 3: Demo of existing elevator, installation of 2nd new high speed elevator. March 2016 thru Sept 2016.

 

Fourth & William Project Manager: Chad Nienhuis -  chadn@spencebrothers.com

Fourth & William Site Superintendent: Dave Fewins  davefewins@spencebrothers.com


Project Concerns/Questions- Call 734-761-3582 (open 24/7)